Search: 15, About, 06/2015
Results
- Clayton B. Wire Playfield Repairs Including Hydraulic Irrigation Replacement (Summer 2015)
... Start Date: May 15, 2015 Estimated Completion Date: August 28, 2015 ... system Project Status: Last Week (7/23/15): Poured Concrete This Week (7/30/15): ...
Bond Project - Clayton B. Wire Campus - 06/22/2015 - 9:47am - 0 comments
- Clayton B. Wire Fire Alarm Replacement
... Start Date: May 15, 2015 Estimated Completion Date: August 28, 2015 ... Project Status: Last Week (7/7/15): Conduit and pulling wire This Week (7/23/15): ...
Bond Project - Clayton B. Wire Campus - 06/22/2015 - 9:46am - 0 comments
- Sacramento High Concrete Repairs at Southwest of Campus
... Start Date: October 15, 2014 Estimated Completion Date: August 28, 2015 ... Project Status: Last Week (7/7/15): Finish grade This Week (7/14/15): ...
Bond Project - Sacramento Charter - 06/18/2015 - 1:52pm - 0 comments
- John Still Covered Walkway Roofing (Summer 2015)
... Start Date: June 15, 2015 Estimated Completion Date: August 28, 2015 ... Project Status: Last Week (7/7/15): Gutters and sheet metal This Week (7/14/15): ...
Bond Project - John Still - 06/22/2015 - 10:10am - 0 comments
- Clayton B. Wire Fencing (Summer 2015)
... Start Date: May 15, 2015 Estimated Completion Date: August 28, 2015 ... Project Status: Last Week (7/7/15): Installing fencing ...
Bond Project - Clayton B. Wire Campus - 06/22/2015 - 9:45am - 0 comments
- Clayton B. Wire Playfield Storm Drainage (Summer 2015)
... Start Date: May 15, 2015 Estimated Completed Date: August 28, 2015 ...
Bond Project - Clayton B. Wire Campus - 06/22/2015 - 9:48am - 0 comments
- Maple Fire Alarm Upgrade – Preschool
... 2015 Estimated Completion Date: August 15, 2015 Project Info: Project ...
Bond Project - Maple Campus - 06/22/2015 - 10:26am - 0 comments